ACTION ALERT: Urge Governor Murphy & NJDEP to Deny Water Permit Applications for Compressor Station 206

2019 is the last phase of the permitting and regulatory process for NESE.

We’ve been at this for a long time, and now is a critical time to have your voices heard where they can make a difference.

THE BALL IS IN GOVERNOR MURPHY’S COURT!

FERC issued their final Environmental Impact Statement on 1/25/19. They claim that any impacts from NESE will be temporary or minor. Though we disagree and have sent comments about our concerns to FERC, we still continue to anticipate that FERC will issue the Certificate of Public Convenience & Necessity since FERC does not seriously consider all that we care about and has only rejected a few pipeline projects (because the company did not have buyers for the gas). The Certificate could be issued as early as the end of February and as late as late April 2019.

Now, it’s up to Governor Murphy and the NJDEP to deny or approve water permit applications. NJDEP can stop the assault on our health, safety and the environment posed by the NESE Project.

Williams/Transco submitted their water permit applications to NJDEP on June 20, 2018. They expect to receive the permits in April 2019, but NJDEP has one calendar year to provide or reject the permit applications.

The proposed Compressor Station 206 and pipeline under Raritan Bay will not be built if Williams/Transco does not get all permits needed from the New Jersey Department of Environmental Protection (NJDEP) & New York Department of Environmental Conservation (NYSDEC).

Please see the new summary of concerns with the NESE Project (PDFs attached) for:

TO DO

Urge Governor Murphy and the NJDEP to look at all aspects of the applications for water permits and hold Williams/Transco to high standards.

Action Alert – NJDEP Update

NJDEP has heard from us about issues with the Freshwater Wetlands Permit Application. 

  • See the attached transcript of the comments (PDF) at the November 5, 2018 hearing at Franklin High School.
  • By November 20 (the deadline to send comments to NJDEP about this permit), over 1,000 comments were sent. 

NJDEP is still reviewing the permit applications and asking Williams/Transco for more information.  Permits are needed from NJDEP for Freshwater Wetlands, Flood Hazard Area, Coastal Wetlands and Waterfront Development.

  • None of the applications have been deemed to be “technically complete”.
  • Applications were received by the NJDEP on June 20, 2018, and they have one calendar year to either grant or deny each permit.

NJDEP stated that there will be another hearing, but the details have not been publicized.  We suspect that the next hearing will be in Old Bridge or Sayreville.

ACTION ALERT: Send Comments to NJDEP by November 20, 2018

DO SOMETHING YOU’LL BE THANKFUL FOR

Speak up for the health, safety & environment of your family, friends and future generations.

Deadline:  Tuesday, November 20, 2018

This is the last date that the NJDEP will consider comments on the Freshwater Wetlands Permit Application of Williams/Transco for the Compressor Station 206 and onland part of the pipeline by Raritan Bay.

REMEMBER:  If all permits are not obtained, the Compressor Station 206 and pipeline near and under the Raritan Bay cannot be built. 

Over 300 concerned residents went to the NJDEP Hearing on November 5, and the 3-minute comments were still being made past 11:00 PM.  That was an amazing showing, but more is needed.

As Abraham Lincoln said in the Lincoln-Douglas debate of 1858,

Public sentiment is everything.
With public sentiment, nothing can fail; without it, nothing can succeed.”

This is the time for all to make their concerns known to the NJDEP.  The power of many is needed to stop the Northeast Supply Enhancement Project from creating risks to our health and safety.  Every comment matters!

COMMENT SAMPLES (.docx):

  1. Incomplete Application that is also not compliant with Stormwater Management Rules
  2. Application does not meet “public need” or “public interest” requirements – long & short versions
  3. Application has concerning impacts on wetlands
  4. Application threatens habitats for threatened & endangered species
  5. Health issues related to Freshwater Wetlands Permit Application
  6. Safety issues related to Freshwater Wetlands Permit Application
  7. Summary of Concerns with the Freshwater Wetlands Permit Application

As Margaret Mead said,

“Never doubt that a small group of thoughtful concerned citizens can change the world.
Indeed it is the only thing that ever has.”

ACTION ALERT: Review NJDEP Application Documents

For the NJDEP hearing, you can review application material from Williams/Transco to NJDEP at:

https://drive.google.com/drive/folders/1Bm6kTq6Fv0JJIC-ra2pOXBH5SPYGWf0c?usp=sharing

These were obtained from the NJDEP through an OPRA request.

The hearing on November 5 is for the Freshwater Wetlands application.

Application for Freshwater Wetlands

Read full ACTION ALERT for the November 5 meeting on TAPinto

Note:  Files on the Google drive with “2017” contain material from the original application that was withdrawn.  The current applications, submitted June 20, 2018, should be marked as 2018.  Not all files are clearly labeled, however.

ACTION ALERT: NJDEP Hearing Monday, November 5

NJDEP scheduled a Hearing for the Wetlands Permit Application for NESE and Compressor Station 206.  See the attached notice.

Show up to let NJDEP know what you think about the proposed Compressor Station 206 & the pipeline in Sayreville & Old Bridge that is planned to also go through Raritan Bay.

DATE:  Monday, November 5, 2018

STARTING TIME:  6:00 PM

PLACE:  Franklin Twp. High School – Auditorium – 500 Elizabeth Ave., Somerset, NJ 08873

Fact-Finding Meetings: 

  • NJDEP staff will facilitate the meeting.
  • People usually get 3 minutes to speak at a microphone in front of the group about their concerns, and a stenographer records it.  It’s not like the FERC meeting where you went into a separate room.
  • Pre-written comments can be submitted at the meeting & can be sent after the meeting.
  • We do expect that pro-NESE people will be there to voice their support (like they were at the FERC public meetings), so we want to have many concerned folks there to tell NJDEP why we do not want NESE.
  • You do not need to be there at 6:00, but if you want to speak, you’ll need to sign-up when you arrive.

Then, NJDEP will give a time period and address for sending them more written comments. 

NJDEP has 90 days after holding fact-finding meetings to issue their decision.

From another hearing, NJDEP provided the following directions:

PUBLIC HEARING RULES OF CONDUCT

The purpose of the hearing is to gather public comment from anyone who wishes to speak. Any action taken by any person that prevents the public from commenting is unacceptable and will not be tolerated. Anyone who violates these rules of conduct may be removed from the hearing.

  • No signs mounted on sticks, or otherwise attached to an object, are allowed within the auditorium
  • No food or drink is allowed within the auditorium
  • Please remain seated until called forward to provide comment
  • No interrupting when someone is speaking
  • No unruly/disruptive behavior (i.e. yelling, chanting, use of foul language)
  • Testimony will be limited to three minutes per speaker

The Department thanks you for your cooperation and participation in this public process

Status of Applications to NJDEP for water permits

Approximately 2,000 mailed and emailed letters were sent to the NJDEP requesting fact-finding meetings (“hearings”) on the water quality permit applications submitted by Williams/Transco on June 20, 2018.  THANK YOU!

NJDEP has started their review of the applications and, on July 18, 2018, they sent a letter to Williams/Transco and FERC identifying deficiencies with the applications.  

NJDEP has one calendar year to grant or deny the permit applications that they received on June 20, 2018, and Williams/Transco now expects to hear the decision in April 2019.

Since NJDEP has 90 days after holding fact-finding meetings to issue their decision, we are anticipating that the fact-finding meetings will be scheduled in the winter of 2018 once they have adequate information for the application reviews.  However, the meeting could be sooner. We’ll let you know when we learn more. Stay tuned!

Fact-Finding Meetings:

  • NJDEP staff will facilitate the meeting at a place that can hold many people.
  • People usually get 3 minutes to speak at a microphone in front of the group about their concerns, and a stenographer records it.  It’s not like the FERC meeting where you went into a separate room.
  • Pre-written comments can be submitted at the meeting & can be sent after the meeting.
  • We do expect that pro-NESE people will be there to voice their support (like they were at the FERC public meetings), so we want to have many concerned folks there to tell NJDEP why we do not want NESE.
  • It’ll probably start around 5:30 PM.  However, you can come later. If you want to speak, you will need to sign-up at the meeting to do this.

Send comments to the NJDEP

  • Commissioner Catherine McCabe: Commissioner@dep.nj.gov
  •  Director Ruth Foster: Ruth.Foster@dep.nj.gov

Williams/Transco submitted new applications for water permits (Freshwater Wetlands, Flood Hazard Area Control, Coastal Wetlands, & Waterfront Development) on June 19, 2018.

  • Tell NJDEP that you want them to hold two (2) public fact-finding meetings – one by the Raritan Bay (Old Bridge / Sayreville) and one by the proposed Compressor Station 206 area (Franklin Township / South Brunswick).
  • Tell NJDEP that you expect them to deny the permits unless they obtain and carefully review all needed information and actually find that the proposed project would not cause harm to the environment, people or wildlife.
  •  Tell NJDEP that an increase in reliance on fossil fuels for energy does not support New Jersey’s goal to transition to renewables and clean energy.

Sign the letter to NJDEP and either mail it or give it to a member of the Task Force to mail
Click here for link to the letter to print, sign & mail

NOTE: A request for fact-finding meetings needs to be in writing to NJDEP and received in Trenton by August 3.

Keep sending comments to FERC

Send comments to FERC that request a “reset” for the DEIS by asking them to publish a revised/supplemental DEIS that addresses all new information and all concerns of the public. Tell FERC that the March 23, 2018 DEIS was missing critical information, dismissed comments of the public & elected officials, and lacked supportive studies or data for FERC’s conclusions. Additionally, Williams/Transco submitted thousands of pages of new information and reports that needs to be reviewed and analyzed in a document that FERC publishes during the time period when the public can truly provide meaningful comments. These submissions were in May and June 2018 – after the DEIS was published & after the end of the “official” time period for sending comments to FERC.

FERC claims that they consider ALL comments they receive. Many people need to let them know that the DEIS was not acceptable.

SEND COMMENTS TO FERC NOW, AND COPY NJDEP.

The DEIS was incomplete & misleading.  Tell FERC that you want a revised or supplemental DEIS and an additional comment period of at least 45 days.

When you send a comment to FERC, also forward that comment to the NJDEP –

  • Commissioner Catherine McCabe: Commissioner@dep.nj.go
  • Director Ruth Foster: Ruth.Foster@dep.nj.gov

You can also forward your comments to your elected officials and ask them to support the opposition to NESE.

2018-05-08 Montgomery Township posts to FERC opposition

Special thanks to Montgomery Township for posting resolution #18-5-112 opposing CP17-101 to FERC on 5/8/2018.  

Includes Memorandum from Montgomery Township Mayor

MT-Mayor_Conforti_Memo

Montgomery Resolution #18-5-112 

MT-Montgomery_res-18-5-112

Map of area where proposed compressor CS206 is relative to Montgomery Township.

MT-map with cs206

FERC acknowledges adverse impact to Princeton Area, but refuses to perform environmental impact analyses.  Instead the Draft Environmental Impact Statement (DEIS) issued by FERC on 3/24/2018 states reasons why FERC doesn’t believe assessing the toxic chemical emissions and high heat/ high discharge of the 50-foot smokestacks.  The DEIS acknowledges real threats, but doesn’t bother to analyze impact or mitigation possibilities – core components of a legitimate DEIS.  The DEIS only underscores that CP17-101 is a Public Threat to New Jersey and not a public convenience.

Montgomery Township and Franklin Township have both sent strong rebukes of the none-material DEIS.  We need more municipalities standing up to this sham to protect the residents of New Jersey.

 

10 days left to comment on NESE DEIS – Ends May 14, 2018

Excellent note from EELC today.  Excellent results from Princeton University team efforts, I love seeing the motions to intervene and comments cascading in my inbox.  Great news that Montgomery Township passed RESOLUTION #18-5-112 opposing CP17-101.  Now we need them to post it to FERC.

There are only 10 days including today.  Several communities have stated they will try to get comments in from their communities.  If anyone has questions or wants clarifications, send it out to the team (stopftcompressor [at] yahoo [dot] com) and you will receive a response.  Surfrider has great comment suggestions and our team has provided a few.  If you have not submitted comments and you are on this distribution list, please make those comments now.

Good attributes for comments:

  1. I oppose this project, I am a registered intervenor.
  2. How it directly impacts you – this will impact people in many different ways even people not in PA/NJ/NYC and that is completely legitimate.
  3. Highlight areas where FERC decided not to assess impact or completely missed.
  4. Identify areas where FERC acknowledges impact as rational that this is currently a Public Threat (not a public convenience) until FERC assesses and mitigates impacts.
  5. Reject the notion that this DEIS statement reflects an actual draft environmental impact statement.  It doesn’t.

Please also email NJDEP and ask why your elected officials have not sent comments after the DEIS.  This is also their critical time to take a stand to protect New Jersey.

10 days,
please make your voice count against